Works Completed over last 4 years
Principle ongoing projects
Projects completed



 PRINCIPAL CONTRACTS PRESENTLY IN PROJECTS :

Name of Project

Employer / Consultant

Contract Period

Percent Complete

Improvement of Tubli Bay Service Road

Ministry of Works & Housing, Roads Directorate

15 Months

55%

Salheya Village Roads

“   “

6 Months

25%

Sitra (Mahazzah) Village Roads

“     “

12 Months

1%

Improvement of Ave. 28/29, Arad

“     “

10 Months

95%

Salmaniya & Sh. Salman H/W Junctions

“   “

6 Months

80%

Buri Village Roads

“     “

12 Months

75%

Road Improvement & Drainage Scheme : Bani Otbah Avenue.

“     “

10 Months

90%

Sh. Salman H/W : Proposed Median Safety Barriers.

“     “

4 Months

85%

Term Contract for CCTV Survey – 2005

Ministry of Works & Housing, SEP & PD

12 Months

30%

East Riffa’a Sewerage Scheme –E2

“     “

21 Months

30 %

West Riffa’a Sewerage Scheme – W4

“     “

20 Months

20%

Tubli Sewerage Scheme, Project 46773

“     “

12 Months

40%

Jid Ali Sewerage Scheme

“     “

18 Months

20%

Saar Sewerage Scheme – Phase 2

“     “

24 Months

20%

Infrastructure works site VE1, Shakhura

Ministry of works & Housing
Housing Projects Directorate

12 Months

30%

Major Pumping Station F1 & Rising Main to Tubli WPCC Project.

“     “

30 Months

40%

Water Transmission Project – Hidd Power & Water Station – Phase 3

“     “

 

20%